Sapura Energy picks up $231m in new jobs

e4319ee0a444bae80e2c14f98542ce02
Sapura Energy has picked up a bounty of about MYR905m ($231.2m) in new contracts.

The offshore services provider said in a press release that its various units had been awarded the contracts for a wide range of jobs in both Malaysia and overseas.

These include Engineering, Procurement, Construction and Commissioning (EPCC) contracts to Sapura Fabrication for two Petronas Carigali projects.

The first is a three-year contract for the Kinarut ERB West Compressor Upgrading Project involving the removal of existing HP compressors and reinstallation of refurbished LP Compressors at EWDP-A, refurbishment of Reinjection Compressors to HP Compressors at offshore at EWG-A, replacement of compressors associated equipment, piping and instrumentation, process and utility tie-ins modifications and other related topside facilities brownfield modifications and improvement at ERB WEST platforms and Kinarut platforms. The contract expires in the third quarter of 2020.  

The second is a four and a half year contract for provision of Minor Engineering, Procurement, Construction and Commissioning (ePCC) for Bokor Betty Brownfield & Rejuvenation, which expires in June 2022.

The contract scope of work comprises of Bokor rejuvenation and host tie-in works at existing platforms including LADR-A and BNG-B and Betty rejuvenation and redevelopment works involving existing platform facilities upgrades, both to support Bokor EOR and redevelopment of the two fields.

Sapura Energy is also doing some work for Hess Exploration and Production Malaysia in the North Malay Basin.

The contract for provision of Engineering, Procurement, Construction, Commissioning Plus Installation (EPCC+I) for FFD Phase 2 Facilities, North Malay Basin comprises engineering, procurement, construction and commissioning of a conventional 3-legged Terminal Wellhead Platform and a Minimal Wellhead Platform, with associated pipelines with an option to provide offshore transportation and installation work.

The works are expected to be completed within second quarter of 2020.

Sapura Energy is also doing transportation work for MISC unit Malaysia Marine and Heavy Engineering (MMHE).

Its Sapura Offshore unit has been awarded a subcontract to undertake transportation and installation works for MMHE's Bokor Central Processing Platform project.  

The contract scope of work comprises of transportation and installation of jackets, piles, bridges and appurtenances. The works are expected to be completed by March 2020.    

Sapura Offshore in addition is providing Offshore/Onshore Pipeline and Terminal Works for Mumbai Port Trust's Fifth Oil Berth Project.

The contract scope of work comprises of installation of 42in diameter submarine pipeline with a 5in diameter composite cable between onshore terminal at Pir Pau (Main Land, Mumbai, India) to the Terminal at Jawahar Dweep and its associated works including trenching, burial and on-shore civil works.

The works are expected to be completed by May 2019.