The main berth has been extended by 105 m providing a total of 865m of quay line on its main berth suitable for the simultaneous berthing of two mega vessels.
In addition, the depth alongside the extended quay is 18m.
Dredging was completed in October with the deepening of the approach channel to 17m and the enlargement of the vessel swing basin to accommodate largest container vessels
The second stage of the expansion is the extension and deepening of the R4 berth to accommodate vessels up to 367m in length.
Meanwhile, four new quay cranes are currently in manufacture in ZPMC in China and are expected to be delivered during October 2017.